Measure Twice, Value-Engineer Once
Basement budgets fail when predictable risks get ignored. Top culprits include: 1) skipping moisture diagnostics (you discover seepage after drywall), 2) vague allowances for high-variance items (tile, lighting), 3) late selections that trigger change-order premiums, 4) underestimated electrical capacity (no room in the panel), and 5) ignoring long-lead items (egress windows, custom millwork) that stall crews.
Build a Scope That Protects the Envelope
Lock funds for vapor barriers, drainage, spray foam at rim joists, ERV, and ducted dehumidification before buying fancy finishes. These invisible items prevent callbacks and finish damage. Phase optional luxuries (projectors, sauna, built-ins) so they can land later without opening walls.
Finish Matrix & Unit Pricing
Replace fuzzy allowances with a Finish Matrix (model numbers, quantities, lead times) and demand unit pricing—per tile square foot, per recessed light, per linear foot of millwork—so substitutions don’t become blank checks. Approve samples before rough inspections to avoid rework.
Procurement & Schedule Discipline
Order long-lead items during permitting and stage materials on labeled racks. Use two-week look-aheads with your GC to track what must be on site to protect the critical path: moisture/structure → MEP rough-ins → inspections → air seal/insulate → drywall → tile/trim → commissioning.
Contingency & Transparency
Hold 10–15% contingency for hidden conditions only, not for predictable upgrades. Require weekly burn-rate reports and a formal change-order process (scope, cost, schedule impact) signed before work proceeds.